Project:   Vans - RV-10   -   VIEW REPORTS
Total Hours:29.5
Total Flight Time:
Total Expense:$175687.69
Start/Last Date:Jan 29, 2019 - No Finish Date
Engine:Lycoming YIO-540-D4A5 RT(Y)
Propeller:Hartzell C2YR-1BFP/F8068D
Panel:Garmin
 
Friendly URL: https://eaabuilderslog.org?s=wcooper

Home or Last Project Picture

Jun 14, 2020     Horizontal Stab Attach       Category: Empennage
Worked on mounting the elevator trim. Noticed some interference with the trim mount bracket and a screw on the bell crank. Had to grind it out to allow free movement. Then had to fish the elevator trim cables through the horizontal stab and out the bottom of the elevator. This was a little tricky but was able to use a flexible lighted claw tool to direct the cable. I used the aftermarket aluminum Elevator Trim Cable Anchor Bracket from iflyrv10.com to secure the trim cable. I was then able to hook up a small 9v battery and switch to check movement of the trim actuator.


 